Chippewa 50th Ave Bridge and CTH J/50th Ave Roundabout

Update for the subject project. Please reach out to Ayres Associates with any questions or concerns.  Contact information is listed below. 

 

Traffic Impacts:

WIS 29 – Off and on ramps at 50th Avenue closed to September 2025. Median shoulder closures with barrier wall at the 50th Avenue bridge. Single lane closures with a speed limit reduction between County X and County J interchanges.

50th Avenue – Closed between 160th and 171st Streets to September 2025. Closed east of County J intersection starting April 14. Access to local residences and businesses will be maintained throughout construction.

County Road J – Shoulder closures between Highway 29 interchange and 51st Avenue starting April 14.

 

 

Work Completed (week of 4/7): Contractor completed installing median pier piling and began excavating for retaining walls.

 

 

Work Lookahead (week of 4/14): Contractor will pour median pier footings and columns, excavate for retaining walls, and begin constructing temporary roadways along County Road J and 50th Avenue.

 

 

Chelsea Seibert , PE | Project Manager/Transportation Engineer

Office: 920.498.1200 | Direct: 715.831.7535 | Cell: 715.205.0436

Ayres Associates Inc. | www.AyresAssociates.com