Traffic Impacts: WIS 29 – Off and on ramps at 50th Avenue closed to September 2025. Median shoulder closures with barrier wall at the 50th Avenue bridge. Single lane closures with a speed limit reduction between County X and County J interchanges. Rolling closure morning of Monday May 5 anticipated.
50th Avenue – Closed between 160th and 171st Streets to September 2025. Traffic is utilizing temporary roadway west of County J intersection. Closed east of County J intersection to September 2025. Access to local residences and businesses will be maintained throughout construction.
County Road J – Shoulder closures between Highway 29 interchange and 51st Avenue. Traffic is utilizing temporary roadway.
Work Completed (week of 5/5): Contractor constructed the median pier cap, constructed the east retaining wall, and completed the construction and traffic switch onto temporary roadways along County Road J and 50th Avenue.
Work Lookahead (week of 5/12): Contractor will complete the median pier cap, construct the east retaining wall coping, construct the west retaining wall, and complete removals and begin earthwork for the second stage of roundabout construction.