Traffic Impacts:
WIS 29 – Off and on ramps at 50th Avenue closed to September 2025. Median shoulder closures with barrier wall at the 50th Avenue bridge. Single lane closures with a speed limit reduction between County X and County J interchanges. Rolling closure morning of Monday May 5 anticipated.
50th Avenue – Closed between 160th and 171st Streets to September 2025. Traffic is utilizing the temporary roadway west of County J intersection. Closed east of County J intersection to September 2025. Access to local residences and businesses will be maintained throughout construction.
County Road J – Shoulder closures between Highway 29 interchange and 51st Avenue. Traffic is utilizing the temporary roadway.
Work Completed (week of 5/12): Contractor finished the median pier cap, began forming the east abutment, constructed west retaining wall, and completed removals for the second stage of roundabout construction.
Work Lookahead (week of 5/19): Contractor will complete forming the east abutment, and begin earthwork and storm sewer installation for the second stage of roundabout construction.