Please ensure Javascript is enabled for purposes of website accessibility
Notice 11-25-2025 : Your Easy Access to Up-to-Date Information—Explore our new site, designed to make your search simple and straightforward.

Weekly Update

Here is the weekly update for the subject project. Please reach out with any questions or concerns.

Traffic Impacts: WIS 29 – Off and on ramps at 50th Avenue closed to September 2025. Median shoulder closures with barrier wall at the 50th Avenue bridge. Single lane closures with a speed limit reduction between County X and County J interchanges. Rolling closure morning of Wednesday April 23.

50th Avenue – Closed between 160th and 171st Streets to September 2025. Closed east of County J intersection starting April 21. Access to local residences and businesses will be maintained throughout construction.

County Road J – Shoulder closures between Highway 29 interchange and 51st Avenue. Traffic switch onto temporary roadways anticipated Wednesday April 30.

Work Completed (week of 4/14): Contractor poured median pier footings, formed pier columns, completed retaining wall excavation, and begin constructing temporary roadways along County Road J and 50th Avenue.

Work Lookahead (week of 4/21): Contractor will pour median pier columns, install east abutment piling, and continue constructing temporary roadways along County Road J and 50th Avenue.