Chippewa 50th Ave Bridge and CTH J/50th Ave Roundabout

Update for the subject project. Please reach out to Ayres Associates with any questions or concerns.  Contact information is listed below. 

Traffic Impacts:

WIS 29 – Off and on ramps at 50th Avenue closed to September 2025. Median shoulder closures with barrier wall and single lane closures with a speed limit reduction at the 50th Avenue bridge.

50th Avenue – Closed between 160th and 171st Streets to September 2025. Access to local residences and businesses will be maintained throughout construction.

County Road J – Will remain open through construction using temporary pavement and flagging.

 

Work Completed (week of 3/24): Contractor excavated for the median pier and worked on removing the existing timber piles.

 

Work Lookahead (week of 3/31): Contractor will complete removing existing timber piles and install median pier piling.

 

 

Chelsea Seibert , PE | Project Manager/Transportation Engineer

Office: 920.498.1200 | Direct: 715.831.7535 | Cell: 715.205.0436

Ayres Associates Inc. | www.AyresAssociates.com

Submit a request