Update for the subject project. Please reach out to Ayres Associates with any questions or concerns. Contact information is listed below.
Traffic Impacts:
WIS 29 – Off and on ramps at 50th Avenue closed to September 2025. Median shoulder closures with barrier wall and single lane closures with a speed limit reduction at the 50th Avenue bridge.
50th Avenue – Closed between 160th and 171st Streets to September 2025. Access to local residences and businesses will be maintained throughout construction.
County Road J – Will remain open through construction using temporary pavement and flagging.
Work Completed (week of 3/24): Contractor excavated for the median pier and worked on removing the existing timber piles.
Work Lookahead (week of 3/31): Contractor will complete removing existing timber piles and install median pier piling.